Project Focus
Industry 4.0 Lean Six Sigma Profitability
Engagement Timeline
2-week Diagnostic 20-week Project
Keywords
Perfomance 4.0 Real time Streaming Analytics
PROJECT GOAL: +20% in Throughput
CONTEXT & CHALLENGE
Utilization of installed capacity was not optimized to meet growing market demand.
Maintenance was centered in corrective maintenance and equipment availability was below target. The CMMS installed was barely utilized.
Equipment efficiency was low and an integrated performance management model was not in place.
Industry 4.0 & Digitalization barely existed: lots of paperwork along with cumbersome and manual filled MS Excel spreadsheets being used as performance reporting tools & KPIs.
Production’s areas lacked tools to dynamic manage weekly and monthly capacity and production plans.
Lack of a formal service level agreements with the commercial area generating frequent changes in planning and scheduling.
PROJECT GOAL: +20% in Throughput
Maintenance was centered in corrective maintenance and equipment availability was below target. The CMMS installed was barely utilized.
Equipment efficiency was low and an integrated performance management model was not in place.
Industry 4.0 & Digitalization barely existed: lots of paperwork along with cumbersome and manual filled MS Excel spreadsheets being used as performance reporting tools & KPIs.
Production’s areas lacked tools to dynamic manage weekly and monthly capacity and production plans.
Lack of a formal service level agreements with the commercial area generating frequent changes in planning and scheduling.
PROJECT GOAL: +20% in Throughput
PROJECT RESULT
in Throughput
0
%
| Operations | -77% Urgency Requests |
| Processes | +21% Cycle Time Reduction & Capacity |
| Maintenance | +27% Equipment Efficiency |
| Maintenance | +7% Equipment Availability |
| Maintenance | -53% MTTR |
| Planning | 90% Weekly Planning Adherence |
| Sales | +17% Sales |
Levering Industry 4.0 solutions and advanced data analytics to achieve sustainable performance
APROACH AND OUTCOMES
Project focused on Planning, Scheduling & Interface, Operational and Maintenance Excellence
PLANNING, SCHEDULING & INTERFACE
Interface agreements with commercial area were implemented, reducing by 77% ‘urgencies and priority’ changes.
Developed KPIs and management tools.
OPERATIONAL EXCELLENCE
Changed the company culture to be more analytical and digital.
Reviewed all the operating procedures and implemented Lean Six Sigma techniques to reduce set up times and product changes by 12%.
The Implementation of tablets at the operator level to automate downtime reporting led to real time gap analysis, elimination of paperwork and manual data collection contributing to the elimination of Excel spreadsheets – “No Excel left behind”.
Industrial Internet of Things (IoT) allowed Real time Streaming Analytics from floor sensors, resulting in truly active management and real time optimization of process parameters.
MAINTENANCE EXCELLENCE
For maintenance, a restructured planning and scheduling process with full digitalization of maintenance operations with existing CMMS resulted in +90% schedule attainment.
Advanced state of the art Data Platform for all management levels connecting all IT systems with fully automated visualization and integrated Artificial Intelligence capabilities such as predictive analytics for equipment failures and advanced modeling to balance and optimize resources.